We strongly advise against adding extra days to an iteration, because it will eat into the next iteration or release development. An experienced team might be flexible enough to do this, but it can derail a new team. Still, desperate times call for desperate measures. If you release every two weeks, you may simply be able to skip doing the actual release, budget time into the next iteration to correct the problems and finish up, and release on the next scheduled date. If testing tasks are being put off or ignored and the release goes ahead, bring up this issue with the team. Did the testing needs change, or is the team taking a chance and sacrificing quality to meet a deadline? The team should cut the release scope if the delivery date is fixed and in jeopardy.

If your release cycle is longer, more like three months, you should know in advance if your release is in jeopardy. You probably have planned an end game of at least two weeks, which will just be for final validation. When you have a longer release cycle, you have more time to determine what you should do, whether it’s dropping functionality or changing the schedule.

If your organization requires certain functionality to be released on a fixed day and last-minute glitches threaten the release, evaluate your alternatives. See if you can continue on your same development cycle but delay the release itself for a day or a week. Maybe the offending piece of code can be backed out temporarily and a patch done later. The customers have the ultimate say in what will work for the business.

Lisa’s Story

On the rare occasions when our team has faced the problem of last-minute showstoppers, we’ve used different approaches according to the situation. If there’s nothing critical that has to be released right now, we sometimes skip the release and release two iterations’ worth on the next release day. If something critical has to go in, we delay the release a day or two. Sometimes we can go ahead and release what we have and do a patch release the next day. On one occasion, we decided to have a special one-week iteration to correct the problems, release, and then go back to the normal two-week iteration schedule.

After more than four years of practicing agile development, we have a stable build almost 100% of the time, and we feel confident about being able to release whenever it’s necessary. We needed a lot of discipline and continual improvement to our process in order to feel that a more flexible approach could work for us. It’s also nice to be able to release a valuable bit of functionality early, if we can. What we’ve worked hard to avoid is falling into a death spiral where we can never release on schedule and we’re always playing catch-up.

Don’t beat yourself up if you can’t release on time. Your team is doing its best. Do spend time analyzing why you got behind schedule, or over-committed, and take action to keep it from happening again.

—Lisa

Work to prevent a “no go” situation with good planning, close collaboration, driving coding with tests, and testing as you code. If your tracking shows the release could be in jeopardy, remove the functionality that can’t be finished, if possible. If something bad and unexpected happens, don’t panic. Involve the whole team and the customer team, and brainstorm about the best solution.

Customer Testing

There are a couple of different ways in which to involve your customers to get their approval or feedback. User Acceptance Testing can be fairly formal, with sign-offs from the business. It signifies acceptance of a release. Alpha or beta testing is a way to get feedback on a product you are looking to release but which is not quite ready.

UAT

User Acceptance Testing (UAT) is important in large customized applications as well as internal applications. It’s performed by all affected business departments to verify usability of the system and to confirm existing and new (emphasis on new) business functionality of the system. Your customers are the ones who have to live with the application, so they need to make sure it works on their system and with their data.

In previous chapters we’ve often talked about getting the customers involved early, but at those times, the testing is done on specific features under development. UAT is usually done after the team decides the quality is good enough to release. Sometimes though, the timeline dictates the release cycle. If that is the case, then try moving the UAT cycle up to run parallel with your end game. The application should be stable enough so that your team could deploy to the customer’s test system at the same time as they deploy to staging.

Janet’s Story

Перейти на страницу:

Похожие книги

1С: Бухгалтерия 8 с нуля
1С: Бухгалтерия 8 с нуля

Книга содержит полное описание приемов и методов работы с программой 1С:Бухгалтерия 8. Рассматривается автоматизация всех основных участков бухгалтерии: учет наличных и безналичных денежных средств, основных средств и НМА, прихода и расхода товарно-материальных ценностей, зарплаты, производства. Описано, как вводить исходные данные, заполнять справочники и каталоги, работать с первичными документами, проводить их по учету, формировать разнообразные отчеты, выводить данные на печать, настраивать программу и использовать ее сервисные функции. Каждый урок содержит подробное описание рассматриваемой темы с детальным разбором и иллюстрированием всех этапов.Для широкого круга пользователей.

Алексей Анатольевич Гладкий

Программирование, программы, базы данных / Программное обеспечение / Бухучет и аудит / Финансы и бизнес / Книги по IT / Словари и Энциклопедии
1С: Управление торговлей 8.2
1С: Управление торговлей 8.2

Современные торговые предприятия предлагают своим клиентам широчайший ассортимент товаров, который исчисляется тысячами и десятками тысяч наименований. Причем многие позиции могут реализовываться на разных условиях: предоплата, отсрочка платежи, скидка, наценка, объем партии, и т.д. Клиенты зачастую делятся на категории – VIP-клиент, обычный клиент, постоянный клиент, мелкооптовый клиент, и т.д. Товарные позиции могут комплектоваться и разукомплектовываться, многие товары подлежат обязательной сертификации и гигиеническим исследованиям, некондиционные позиции необходимо списывать, на складах периодически должна проводиться инвентаризация, каждая компания должна иметь свою маркетинговую политику и т.д., вообщем – современное торговое предприятие представляет живой организм, находящийся в постоянном движении.Очевидно, что вся эта кипучая деятельность требует автоматизации. Для решения этой задачи существуют специальные программные средства, и в этой книге мы познакомим вам с самым популярным продуктом, предназначенным для автоматизации деятельности торгового предприятия – «1С Управление торговлей», которое реализовано на новейшей технологической платформе версии 1С 8.2.

Алексей Анатольевич Гладкий

Финансы / Программирование, программы, базы данных