Bobby[2]
didn’t worry about the Navy very long, because we gave him far bigger worries than that: four months before we were supposed to test-fly Have Blue our shop mechanics went out on strike.The International Association of Machinists’ negotiations with the Lockheed corporation on a new two-year contract failed in late August 1977. Our workers hit the bricks just as Have Blue was going into final assembly, perched on its jig with no hydraulic system, no fuel system, no electronics or landing gear. There seemed to be no way we would be ready to fly by December 1, our target date, and our bean counters wanted to inform the Air Force brass that we would be delayed one day for each day of the strike. But Bob Murphy, our veteran shop superintendent, insisted that he could get the job done on time and meet our commitment for first flight. To Murphy, it was a matter of stubborn Skunk Works pride.
Bob put together a shop crew of thirty-five managers and engineers who worked twelve hours a day, seven days a week, over the next two months. Fortunately, most of our designers were all great tinkerers, which is probably why they were drawn to engineering in the first place. Murphy had Beswick, our flight test head, working with a shop supervisor named Dick Madison assembling the landing gear. Murphy himself put in the ejection seat and flight controls; another shop supervisor named John Stanley worked alone on the fuel system. Gradually, the airplane began coming together, so that by early November Have Blue underwent strain gauge calibrations and fuel system checkout. Because Have Blue was about the most classified project in the free world, it couldn’t be rolled outdoors, so the guys defied rules and regulations and ran fuel lines underneath the hangar doors to tank up the airplane and test for leaks. But how could we run engine tests?
Murphy figured out a way. He rolled out the plane after dark to a nearby blast fence about three hundred yards from the Burbank Airport main runway. On either side he placed two tractor trailer vans and hung off one end a large sheet of canvas. It was a jerry-built open-ended hangar that shielded Have Blue from view; security approved provided we had the airplane in the hangar before dawn.
Meanwhile an independent engineering review team, composed entirely of civil servants from Wright Field in Ohio, flew to Burbank to inspect and evaluate our entire program. They had nothing but praise for our effort and progress, but I was extremely put out by their visit. Never before in the entire history of the Skunk Works had we been so closely supervised and directed by the customer. “Why in hell do we have to prove to a government team that we knew what we were doing?” I argued in vain to Jack Twigg, our assigned Air Force program manager. This was an insult to our cherished way of doing things. But all of us sensed that the old Skunk Works valued independence was doomed to become a nostalgic memory of yesteryear, like a dime cup of coffee.
We had lived and died by fourteen basic operating rules that Kelly had written forty years earlier, one night while half in the bag. They had worked for him and they worked for me:
1. The Skunk Works program manager must be delegated practically complete control of his program in all aspects. He should have the authority to make quick decisions regarding technical, financial, or operational matters.
2. Strong but
3. The number of people having any connection with the project must be restricted in an almost vicious manner. Use a small number of good people.
4. Very simple drawing and drawing release system with great flexibility for making changes must be provided in order to make schedule recovery in the face of failures.
5. There must be a minimum number of reports required, but important work must be recorded thoroughly.
6. There must be a monthly cost review covering not only what has been spent and committed but also projected costs to the conclusion of the program. Don’t have the books ninety days late and don’t surprise the customer with sudden overruns.
7. The contractor must be delegated and must assume more than normal responsibility to get good vendor bids for subcontract on the project. Commercial bid procedures are often better than military ones.
8. The inspection system as currently used by the Skunk Works, which has been approved by both the Air Force and the Navy, meets the intent of existing military requirements and should be used on new projects. Push basic inspection responsibility back to the subcontractors and vendors. Don’t duplicate so much inspection.
9. The contractor must be delegated the authority to test his final product in flight. He can and must test it in the initial stages.
10. The specifications applying to the hardware must be agreed to in advance of contracting.